2015 Renovation Event #3 - Field 1
Thursday, April 23 2015
All Work completed on Field #1
remove all items from the Green Bin, Wash the bin and reorganize the contents
Line base paths, infield edge, pitching mound, and home plate circle with string and then edge in preparation of "Action Hoe" - Need additional Gas or Electric Power Edger
Need 3-4 "Action Hoes" - persons follow the
Using Roundup spray, spray into the dirt at the edge of newly cut edges to prevent grass from growing into base paths
Rakes needed - Rake and remove all grass from base paths - DIRT MUST BE REMOVED FROM CUT GRASS or trash bins become too heavy for waster removal contractors.
Batters box clay is too low and base edge is exposed creating potential safety issue. Need to raise the area around the base by 1/2"
Flat head shovels needed - Need person to Rototill and 4 persons to spread mix with shovels
Add mound mix to pitching mound and add second pitching rubber under the dirt.
RESERVED - M. Killingsworth
Contact the event organizers: Eric Schultheiss